INDOT Provides Update On U.S. 30 Closure East Of Ind. 331
INDOT Provides Update On U.S. 30 Closure East Of Ind. 331
Posted
Staff Report-
INDOT Provides Update On U.S. 30 Closure East Of Ind. 331MARSHALL COUNTY – After going through the emergency contract procedure, the Indiana Department of Transportation has signed the Emergency Award and Notice to Proceed and contracted Woodruff to repair the culvert on U.S. 30 just east of Ind. 331.
Repairs in the westbound lanes that are currently closed will begin on Tuesday, and U.S. 30 westbound is expected to reopen by the end of July, according to a news release from INDOT Friday. Motorists will need to continue seeking an alternate route. The official detour follows Ind. 19, Ind. 10 and Ind. 331.
This is a full pipe repair across the entire roadway so work will move to the eastbound lanes after the westbound side is complete. INDOT is still working on maintenance of traffic plans for this phase of work and will provide more information as it is available, the release states.